Skip to main content

Indorama Ventures – Restoration Project

Location: Westlake, Louisiana

project quick facts

  • Duration: August 15, 2020 – September 30, 2021
  • Contract Type: Time and Materials 
  • Workhours: 560005 
  • Percentage of Labor Self-Performed: 80% 
  • OSHA Recordables: ZERO 
  • Contract Value: $51 MM
  • Subcontractors:

turner self-performed

Mechanical and Piping

  • 127 new control valves 
  • 38 exchangers (open, cleaned, and inspected)
  • 4 drums (opened, cleaned, and inspected) 
  • 71.5 tons of steel erected 
  • 4500 Ft piping demoed 

Scaffolding, Insulation, Painting and Abatement

  • 500+ Scaffolds Built 
  • 29,867 Ft of Insulation 

Electrical and Instrumentation

  • 450,000 Ft of wire installed and terminated 
  • 49 junction boxes installed 
  • 590 Instruments and valves wired, and function tested
  • 5000 Ft of tubing installed 
  • 70,000 Ft Conduit installed 

Crane and Rigging: Over 15 total cranes to support the overall project

  • 600 ton and 500-ton tandem lifts for removal and installation of mall duct, removal, and installation of economizer 
  • 190-ton crane support for stack inspections
  • Provided specialized transportation services to transport all demo equipment and new equipment to and from unit