Rebuild of Boiler at Shell Norco

rebuild of boiler at shell norco

Norco, Louisiana

Turner Industries completed a turnaround at Shell in Norco, Louisiana, rebuilding one of the plant boilers. 

  • The scope of work included the removal and reinstallation of about half of the drum internals, installation of flanges and valves, removal and reinstallation of sample tubes, gaskets, and a 25-foot-long superheat vent line. 
  • The critical path of the job was to remove and reinstall the entire economizer – consisting of 38 panels with 76 buttwelds outside the boiler. This work also included removing and replacing a 12’ X 28’ expansion joint directly above the economizer. 
  • Discovery work during the outage turned the replacement of two other expansion joints into critical path work along with the economizer work. 

project quick facts

  • Duration: 4 Weeks 
  • Workhours: 31,000  
  • Peak Headcount: 125 
  • Welds: 132 
  • Valves Replaced: 32 
  • OSHA Recordables: ZERO 