Turner Industries successfully completed a two-phase project for Evonik at their Mapleton, Illinois facility, finishing 1½ weeks ahead of schedule while maintaining an exemplary safety record.
The project involved civil work including demolition, installation of two 43-foot diameter tank foundations, 10 drilled concrete piers, pump pads, and area paving. The structural phase featured steel demolition, tie-ins, and erection of a 100-foot-long catwalk positioned 36 feet above ground level.
When tank construction delays threatened the timeline, Turner Industries demonstrated its adaptability by mobilizing early to work alongside the tank constructor rather than waiting for sequential completion. This proactive approach enabled the accelerated finish while coordinating crane operations with multiple contractors, and the project achieved zero first aids and zero incidents.